Construction Law

By Brodie Roberts, Founder, Roberts Litigation · Brisbane, Queensland | Last reviewed: October 2026

For a Queensland builder or trade contractor, the licence is the business. Without it, you cannot lawfully carry out most building work or get paid for it. Yet licence compliance usually sits behind pricing, site safety and subcontractor schedules until a letter from the Queensland Building and Construction Commission (QBCC) arrives. How a contractor handles the first few weeks after that letter often decides whether the issue is resolved quietly or turns into a suspension, a disciplinary finding or a costly dispute.

The short answer: Read every QBCC notice the day it arrives, note the response date, and answer with evidence rather than argument. Most QBCC decisions can be reviewed, but internal review and Queensland Civil and Administrative Tribunal (QCAT) review applications are generally subject to strict 28-day time limits, and missing them can leave a decision in place permanently.

The Notices Contractors Most Often Receive

Notice or decisionWhat it usually involvesWhat to watch for
Direction to rectifyQBCC directs a contractor to fix defective or incomplete building workThe rectification deadline; the right to seek review; consequences of non-compliance
Notice of intention to suspend or cancel a licenceAlleged failure to meet licensing requirements, including minimum financial requirementsThe date to respond and the evidence QBCC has asked for
Requests for financial informationEvidence of net tangible assets or other financial requirementsAccuracy of accounts and who prepared them
Disciplinary or show cause correspondenceProposed action for alleged breaches of the Act or licence conditionsThe grounds alleged and the opportunity to make submissions

The Queensland Building and Construction Commission Act 1991 gives QBCC broad powers, including directing rectification of defective work and suspending or cancelling licences. According to QBCC’s guidance on licence issues, before cancelling a licence QBCC notifies the licensee in writing of its intention and the reasons, and licensees who can no longer meet their minimum financial requirements must tell QBCC.

Why “Wait and See” Is Risky

Many contractors assume that good workmanship or a long relationship with a client will carry the day. Regulatory decisions do not work that way. They turn on the legislation, the evidence in front of the decision-maker and whether deadlines were met. A late response can mean a decision is made without your side of the story, and a direction to rectify that is not complied with can lead to disciplinary action, insurance claims against the contractor and recovery action by QBCC.

Directions to rectify are often contested on the facts: whether the work was actually defective, whether it was within the contractor’s scope, or whether the homeowner or another trade caused the problem. Those arguments need independent evidence, not just a contractor’s word.

Three Rules for Handling a Notice

1. Stop and Document

Record the date and method by which the notice was received, keep the envelope or email, and read it in full. Identify exactly what is alleged and what is being asked. Avoid informal conversations with investigators about the substance of the issue until you understand your position and rights.

2. Diarise Every Deadline

Statutory deadlines do not move because a project is busy. Note the response date in the notice, any rectification period and the review deadline. Under the Act, an application for internal review of a reviewable decision generally must be made within 28 days, and QCAT’s guidance on QBCC reviews explains that an external review application is usually subject to a 28-day or other statutory timeframe, with internal review generally required first. Extensions are possible but not guaranteed; tribunals look closely at the reason for the delay and the strength of the case.

3. Respond With Evidence, Not Emotion

Base a response on documents: the contract and scope of works, variations, inspection and certification records, photographs, engineering or expert reports, and financial statements prepared by a qualified accountant. Keep correspondence with homeowners and QBCC factual and professional. Combative emails are often exhibits later.

Review Rights and Stays

If a decision goes against you, the usual path is an internal review by QBCC followed, if necessary, by an application to QCAT. Filing with QCAT before an internal review is finished generally ends the internal review. Where a decision would cause immediate harm, such as a licence suspension, it may be possible to ask QCAT to stay the decision while the review is heard, supported by evidence of why a stay is justified. Some decisions cannot be reviewed once certain steps have been taken, which is another reason not to delay.

When to Get Legal Advice

Getting advice early is usually cheaper than fixing a decision later. Contractors who receive a direction to rectify, a notice of intention to suspend or cancel, or a request for financial information they are unsure how to answer often speak with a QBCC lawyer before responding, so the first submission is framed around the right legal tests. Licensing disputes share features with other professional licence matters; this overview of strategies for defending a professional licence discusses common approaches. Where a regulatory issue turns into a commercial dispute with a client or developer, experienced litigation lawyers may also be needed.

A QBCC notice is not the end of a business, but it is a deadline. Contractors who act quickly, keep their records in order, and respond with evidence are best positioned to protect their licence.

Authorities & Sources

  1. Queensland Building and Construction Commission Act 1991 (Qld)
  2. QBCC: Licence issues
  3. QCAT: Queensland Building and Construction Commission reviews

Disclaimer

This article provides general information about Queensland building regulation and is not legal advice. Reading it does not create a lawyer-client relationship. Time limits and review rights depend on the specific decision and its date. Contractors should obtain advice from a Queensland lawyer about their own circumstances.

About Author

Brodie Roberts is the founder of Roberts Litigation, a Brisbane law firm he launched in 2025. His career has been devoted exclusively to disputes work, and he previously practised as a senior associate before establishing the firm. He acts in complex commercial disputes, construction and infrastructure matters, and insolvency litigation, including QBCC licensing and rectification issues for builders and contractors. Roberts Litigation advises clients across Queensland on regulatory, contractual and payment disputes in the building and construction industry.